Taylors, SC · Upstate

Packs Mountain

Ground-Up Single-Family · Hillside Spec

In construction · Windows in

  1. 01

  2. 02

  3. 03

  4. 04Construction

  5. 05

Packs Mountain — current progress on site

01

The project

A hillside spec home on a wooded lot in the Upstate. Cleared in March, foundation in May, framed in July, shingled in September — about six months from standing timber to dry-in.

Packs Mountain is a ground-up spec home on a steep, wooded lot in Taylors. On a site like this the access is the deal: we cut the pad, built dry-stack stone retaining walls, and ran a gravel drive up the slope before the first block was laid. The house went from a cleared pad in March to a shingled roof in September. The project is held in its own single-purpose entity with seller-carried land, a committed senior construction lender, and joint-venture equity partners.

01
Hillside lot · wooded, sloped site
02
Cut pad, stone retaining walls, gravel drive
03
Block foundation, stick-framed
04
For-sale spec home

02

From site to structure

What we started with

March 2026 — cleared, pad cut, survey stakes in
photoMarch 2026 — cleared, pad cut, survey stakes in

What we're building

Finished home — rendering
renderingFinished home — rendering
Floor plan
planFloor plan

03

Progress

  1. March 2026

    Cleared and staked

    Trees down, pad cut, survey stakes in.

    Packs Mountain, March 2026: Cleared and staked
  2. May–June 2026

    Retaining walls and foundation

    Dry-stack stone walls hold the hill; block foundation walls go up.

    Packs Mountain, May–June 2026: Retaining walls and foundation
  3. July 2026

    Framed

    Walls and roof structure up.

    Packs Mountain, July 2026: Framed
  4. August 2026

    Roof deck and drive

    Roof decked; gravel drive and walls finished up the slope.

    Packs Mountain, August 2026: Roof deck and drive
  5. September 2026

    Shingled — dry-in

    Roof on. The structure is sealed and the schedule stabilizes.

    Packs Mountain, September 2026: Shingled — dry-in
  6. September 2026

    Rough-ins: HVAC and electrical

    Air handler and ductwork up in the attic; wiring and boxes run through the framing.

    Packs Mountain, September 2026: Rough-ins: HVAC and electrical
  7. Mid-September 2026

    Windows and doors in

    Windows set and French doors hung on the lower level. The house is closing in.

    Packs Mountain, Mid-September 2026: Windows and doors in

04

How it's structured

  • Single-purpose entity
  • Seller-carried land
  • Senior construction loan
  • JV equity partners
  • For-sale exit

Offered only to verified accredited investors under Rule 506(c). See the investor portal for offering documents.

05

What comes next

  1. 01Exterior finishes
  2. 02Finish rough-ins, then insulation and drywall
  3. 03Interior build-out
  4. 04Target completion: winter 2026

Next stage: Complete